New Construction Electrical in New Hampshire: From Temporary Power to Final Trim

Published 9 min readBy Copp Electric

Temporary construction power pole with meter, disconnect, and four weatherproof outlets braced at a New Hampshire building site

New construction electrical runs in a fixed order: temporary power, service entrance, underground feeders, rough-in, rough inspection, then trim and final. Each stage gates the next, which means the electrician's calendar is really the drywall calendar. Pricing the package off the prints is what keeps a build moving instead of waiting.

Key takeaways

  • Temporary power is the first electrical item on any site, and every trade after you depends on it, so it gets set before anyone needs to plug in a saw.
  • The order is fixed: temp power, service, underground, rough-in, rough inspection, insulation and drywall, then trim and final. There is no shortcut through the middle of it.
  • The rough inspection is the real deadline on a build. Drywall cannot legally cover the walls until it passes, so a failed or missed rough costs the whole schedule, not just the electrician's day.
  • Running conduit for a generator, an EV charger, or a future garage during framing costs a fraction of retrofitting it once the walls are closed and the driveway is poured.
  • New Hampshire adds its own variables: ledge on underground runs, a well pump and septic pump that belong in the load calculation, and town inspection calendars that tighten every fall.

It starts with temporary power

The first electrical work on a new build happens before there is a house to wire. A temporary power pole goes in near the road: a meter, a disconnect, and a bank of weatherproof outlets on a braced post, fed from the utility and permitted like any other service.

It looks like a small thing. It is not. Framers, the well driller, the HVAC crew, and the finish trades all pull off that pole for months. If it is not set when the foundation crew arrives, everybody is running generators and cords, and the whole site slows to the speed of extension cords.

Because it is a metered, permitted service, it has a lead time of its own. The utility has to come out. The town has to inspect it. That is why temp power gets booked at the same time as the foundation, not the week the framers show up.

One temp pole serves the whole build, so it is worth putting it somewhere the excavator will not have to work around for the next eight months. We walk that with the builder before it goes in the ground.

Setting the permanent service

The permanent service is the meter socket, the service disconnect, and the conductors that carry power from the utility's point of connection to the panel. On a lot with no house on it yet, that often means a pole board set at the property line while the driveway and foundation are still being worked out.

This is also where a decision gets made that the homeowner will live with for thirty years: how much service the house gets. A hundred amps used to be normal. It is not adequate for a modern New Hampshire build with a heat pump, an induction range, a heat pump water heater, a well pump, and an EV in the driveway. Two hundred amps is the working baseline, and some builds justify more.

The load calculation is done from the plans and the actual appliance schedule, not from square footage. That number decides the service size, the panel, and whether there is room left over for the things nobody has bought yet.

Underground feeders, and the ledge problem

Plenty of builds around here put the service underground, and most put at least one feeder underground: to a detached garage, a barn, a well house, or a pump. Underground is cleaner to look at and far less exposed to the ice storms that take down overhead drops every winter.

It is also the stage where New Hampshire charges rent. Ledge is the single biggest variable on any trench in this region, and it does not show up on a plan set. A run that would be a morning's work in sand can turn into a hammer and a very different number when the bucket hits rock four feet in.

The sequence matters too. Conduit goes in the trench with the right depth, the right sweeps at both ends, and warning tape above it, and then the trench gets inspected while it is still open. Backfilling before that inspection means digging it out again.

Trenching is coordinated with the excavator, so the electrical trench gets cut while the machine is already on site for footings and utilities. Bringing it back for one trench later is a line item nobody enjoys.

Rough-in is where the house is actually designed

Rough-in is every wire in the building, run and stapled and boxed, before insulation and drywall close the walls. It is the largest phase of the electrical package and the one where the most decisions get locked in permanently.

Every outlet, every switch, every three-way, every can light, every appliance circuit, every data drop, and every location a fixture will eventually hang gets committed during rough-in. Moving a switch afterward means opening a wall. Adding an island pendant afterward means opening a ceiling.

This is the moment to walk the framed house with the electrician and the homeowner and talk about how the rooms will really be used. Where does the coffee maker live. Which side of the bed does the phone charge on. Does the island get pendants or a single fixture. Is the TV over the fireplace, and does that need a recessed box behind it. Fifteen minutes of that walk saves a decade of extension cords.

What gets decided permanently at rough-in
DecisionCost to change later
Outlet and switch locationsOpen the wall, patch, prime, paint
Recessed lighting layoutOpen the ceiling, and the layout rarely comes out even
Island and pendant boxesCeiling work over finished cabinetry and countertop
Appliance and HVAC circuitsNew home run through finished walls, or a surface raceway
Panel and subpanel locationEffectively fixed once drywall is up
Generator and EV conduitTrenching a finished driveway and lawn, plus wall work
Data and low-voltage dropsFishing walls, or living with wireless where wired was better

The rough inspection is the real deadline

Once rough-in is complete, the town's electrical inspector walks the open walls. Nothing gets covered until that inspection passes. Not insulation, not drywall, not the blower door.

This is why the electrician's schedule is the builder's schedule. If rough-in is late, or if the rough fails and needs corrections, the insulation crew loses their date, the drywall crew loses theirs, and every trade behind them slides. A single missed inspection window can be a week.

The way to avoid that is unglamorous: rough in to code the first time, book the inspection before the work is finished rather than after, and be on site to meet the inspector so questions get answered in the moment instead of turning into a reinspection.

Permits and inspections are not paperwork you push through at the end. On a new build they are scheduling milestones, and they belong on the same calendar as the framing and drywall dates.

Rough in now for what you will want later

The cheapest electrical work on any build is the work done while the walls are open and the trench is already dug. The most expensive version of the same work is the one done three years later.

None of the items below require buying the equipment now. They require running conduit, leaving a pull string, and reserving space in the panel. That is a small line item during framing and a large project afterward.

  • Conduit and a transfer switch location for a standby generator, plus a pad location that clears windows and doors
  • A 240 volt circuit or an empty conduit to the garage wall for an EV charger, sized for a 48 amp charger even if the first car is a plug-in hybrid
  • An empty conduit under the driveway before it is paved, for anything at all
  • A feeder and subpanel provision to a future detached garage, shop, or barn
  • Circuits for a hot tub pad, an outdoor kitchen, or landscape lighting
  • Data drops to the office, the TV walls, and wherever the access points will go
  • Panel space and a spare conduit from the panel to the attic and to the basement

Rough in for a generator and an EV charger even if the homeowner is unsure. Conduit is cheap. Trenching a finished lawn and opening a finished wall is not.

Trim and final: the only part anyone sees

Trim happens after paint. Devices go in, plates go on, fixtures get hung, the panel gets a directory that a stranger could read, and every circuit gets tested.

It is the fastest-looking phase and the one that gets judged hardest, because it is the only electrical work the homeowner will ever look at. Crooked plates and a panel labeled in pencil are what people remember about an otherwise flawless rough-in.

Then the final inspection, and the walkthrough: where the panel is, what the main looks like, which breaker is the well, how the GFCIs reset, and what to do when a breaker trips at eleven at night.

The full sequence, and what each stage gates

New construction electrical, stage by stage
StageWhat happensWhat it holds up
Plan reviewPrice from the prints, load calculation, flag anything that fails inspection laterThe proposal, and the service size decision
Temporary powerMetered temp pole set, permitted and inspectedEvery trade on site
Service and undergroundMeter socket, service conductors, trenched feeders and conduitTrench inspection, then backfill and grading
Rough-inAll circuits run, boxed, and stapled in open wallsInsulation and drywall
Rough inspectionTown electrical inspector walks the open wallsEverything after it. This is the schedule.
TrimDevices, plates, fixtures, panel directoryFinal inspection and the certificate of occupancy
Final inspectionInspector signs off on the finished systemOccupancy

The stages that are not in our hands are the utility connection and the town's inspection calendar, and both of them get longer as the fall goes on. That is the argument for booking the electrical package early rather than when the framers are already up.

How this works with your builder

Most of our new construction work is booked through builders and general contractors, and the job is as much about holding a date as it is about wire. We price from the plan set and return a line-item proposal that separates temp power, service and underground, rough, trim, fixtures, and any generator or EV provisions, so nothing appears as a surprise change order in month six.

If you are a homeowner building your own place, the same thing applies one step earlier: get the electrical scoped before framing starts, not after, so the decisions that get locked in at rough-in are decisions somebody actually made.

We work across Franklin, Tilton, Northfield, Belmont, Laconia, Concord, Sanbornton, Boscawen, plus Bristol, Center Harbor, Gilford, Loudon, Meredith, Moultonborough, and New London.

Frequently asked questions

Who sets up temporary power on a new construction site?
The electrician does. A temporary power pole is a metered, permitted service with a meter, a disconnect, and weatherproof outlets, and it needs a utility connection and a town inspection like any other service. It should be scheduled alongside the foundation, because every trade after that point works off it.
When should I book an electrician for a new build?
At the plan stage, before framing starts. The load calculation and service size come off the plans, the temp power pole has a utility and inspection lead time of its own, and rough-in has to be slotted into the framing and drywall calendar. Calling once the walls are up means taking whatever date is left.
What is the difference between rough-in and trim?
Rough-in is all the wiring run inside open walls and ceilings before insulation and drywall: circuits, boxes, and every switch and outlet location. Trim happens after paint and is the visible part: devices, plates, fixtures, the panel directory, and testing. Rough-in is where the decisions are made; trim is where they show up.
What happens at a rough electrical inspection?
The town's electrical inspector walks the open walls and checks that the wiring method, box fill, staple spacing, circuit sizing, grounding, and required AFCI and GFCI protection all meet code. Nothing can be covered until it passes, so insulation and drywall are both waiting on it.
Should I rough in for a generator or EV charger during construction?
Almost always. Running conduit and reserving a transfer switch location or a 240 volt circuit while the walls are open and the trench is already cut costs a small fraction of doing it later, and it commits you to nothing. Retrofitting the same thing means trenching a finished driveway and opening a finished wall.
How much does new construction wiring cost in New Hampshire?
It is priced per plan set, not per square foot. Bring us the prints and you get a line-item proposal covering temporary power, service and underground, rough-in, trim, fixtures, and any generator or EV provisions you want roughed in now. We would rather give you a real number off the drawings than a guess over the phone.
Do you work directly with builders and general contractors?
Yes. Most of our new construction work comes through builders and GCs around Franklin, Tilton, and Laconia, and we schedule rough-in and trim around the framing and drywall calendar and meet the inspector ourselves so drywall is never waiting on us.